Compressor Station
Project Name: Compressor Station
Client: Anadarko (OXY)
Location: Denver Colorado
Timeline: 2018-2019
Project Summary:
The station is designed to meet a design flowrate 140MMSCFD of produced gas in the DJ area. Major equipment for the station included the following:
- Inlet slug catcher/separator vessel
- Water handling vessel
- Five (3) Hydration unit each with a design flowrate of 35MMSCFD
- Five (5) 2500BHP natural gas-driven reciprocating compressor
- Five (3) BETX condenser/coalescing filter separator skid
- Five (3) Vapor recovery unit
- LACT Unit
- Centralize instrument air system
- Fuel gas metering skid
- Analyzer building
- Fuel gas letdown skid
- MCC building
- 720 KW generator
The station was designed with the capacity to add two (2) future 2500BHP electric driven reciprocating compressors, and one additional dehydration package.
Roles and Responsibilities:
- Process simulated the station using VMGSim
- Sized all the major equipment
- Completed Hydraulic line sizing
- Conducted flare system study and Analysis
- Verified and approved all third-party shop drawings
- Structural members design and selection for all pipe modules
- Piling sizing
- Foundation and footing design for the inlet slug catcher and water vessel
- Produced over 2000 shop fabricated drawings
- Coordinated with vendors and suppliers on procurement related activities
Canadian Head Office - Calgary
Suite 1610, 555 4th Ave SW
Calgary AB, Canada
T2P 3E7
Calgary AB, Canada
T2P 3E7
US Head Office - Denver, CO
Suite 600H, 1630 Welton Street
Denver, CO
80202
US Field Office - Gillette, WY
413 South Gillette Avenue
Gillette, WY
82716
Get in Touch Using our Contact Form Below
or call Now: