Project Name: Solution Gas Conservation

Client: PennWest Exploration

Location: Peace River, AB, Canada

Timeline: 2016-2018

Project Summary:

Due to tighter regulations surrounding solution gas venting from oil storage tanks, GRD was involved in providing onsite construction management to eliminate the venting of solution from oil storage tanks in the Peace River Area.

The scope of the project includes the following:

  • Thirty (30) Oil storage battery
  • Install Thirty (30) fuel gas skids
  • Install Thirty (30) vapour recovery unit
  • Install solution gas header system to each site

Roles and Responsibilities:

  • Client Representation at Pre-Inspection Meetings
  • Document Review / Traceability – Material Certificates
  • Visual Inspection / Dimensional Control
  • Witness Testing:
    • Performance Test
    • Hydrostatic Pressure Test
    • Balance Test, Leak Test
    • Ultrasonic Test (UT),
    • Radiographic Test (RT)
    • Magnetic Particle Identification (MPI), Thermographic Test, Liquid / Dye Penetrant Test (LPI/DPI), Pneumatic Test, Functional Test,
  • Management of Equipment Installation
  • Management of Site Construction Contractors
  • Coordination of all Third-Party Vendors
  • Coordination of Loose Shipped Equipment and Specialty Items
  • Construction Hand Over
  • Commissioning and Start-up Assistance

Canadian Head Office - Calgary

Suite 801, 110 – 12 Avenue SW
Calgary AB, Canada
T2R 0G7

US Head Office - Denver, CO

Suite 600H, 1630 Welton Street
Denver, CO
80202

US Field Office - Gillette, WY

413 South Gillette Avenue
Gillette, WY
82716

Get in Touch Using our Contact Form Below

or call Now:

• CANADA +1.403.202.7479
• USA +1.303.342.3364